# Federal Infrastructure Milestone Monitor — workflow

## Choose this tool

Maintain a source-linked review list for mining, transmission and other infrastructure projects. Collect official review milestones, target dates, baseline dates and published completion dates from the federal Permitting Dashboard, then compare them with your last saved observations.

Useful output columns: `recordId`, `projectTitle`, `sector`, `projectStatus`, `milestoneName`, `targetDate`.

## Practical workflow

Copy this input into Console's JSON editor. It requests up to five milestones for in-progress mining projects in the default FAST-41 Covered and Transparency categories. No API key, login or proxy subscription is required.

```json
{
  "sectors": [
    "Mining"
  ],
  "maxSourceEntries": 5,
  "maxResults": 5
}
```

Open **Saved observations** or **CSV export** for the rows, then **Run report** for coverage. Repeated project titles are expected because a project can have many milestones. Empty input saves up to five rows from a larger default source window of 100 milestones.

## Check the fit

One result is one milestone within a project action. Collection uses a bounded source window before keyword filtering; it is not a complete dashboard history or all matching projects. Dashboard inclusion does not establish funding or approval. Date-only values stay date-only. Changes-only requires comparePrevious and onlyChanges together; inspect source-window coverage, failed records and history commits before interpreting revisions.

## Real output sample

One selected row from a 2026-10-17 run. One saved row, selected scalar columns only. Contact details, patient demographics and long text are omitted. Original values and nulls are preserved.

Run: tHB3jJieY6pmVoBPb. Summary status: ok. Incomplete: false.

Historical output from this run; the current example input is a separate starting configuration and may produce different records.

```json
{
  "recordId": "1169464596",
  "projectTitle": "Michigan Potash",
  "sector": "Mining",
  "projectStatus": "In Progress",
  "milestoneName": "Initial application submitted (Applicant Action)",
  "targetDate": "2022-12-30",
  "baselineTargetDate": "2022-12-30",
  "baselineTargetShiftDays": 0,
  "actualCompletionDate": "2022-12-30",
  "sourceUrl": "https://data.permits.performance.gov/resource/mcm3-xbid.json",
  "observedAt": "2026-10-17T15:56:17.957Z"
}
```

## Combine with companion tools

Each Actor runs separately with its own inputs, authorization and pricing. These instructions do not configure automatic execution.

### [EIA Power Project Monitor](https://mayd-it.com/data-tools/actors/eia-power-project-monitor/)

Monitor planned US generators, capacity and scheduled operation months from official EIA reporting. Filter project watchlists and compare confirmed saved observations. Keep this EIA Power Project Monitor evidence alongside the original source in a reviewed infrastructure research workflow.

1. Choose the corresponding source target in this second Actor’s own input form; no automatic field transfer is configured.
2. Keep both original source URLs and observation dates in your review sheet; reconcile identities manually.

A published milestone, application or project listing does not establish construction completion, available capacity or investability. Match official project evidence and dates.

### [US Building Permits Scraper - 10 Cities, One Schema](https://mayd-it.com/data-tools/actors/us-building-permits-scraper/)

Scrape US building permits from 10 city open-data portals into one clean schema. Contractor and applicant leads with address, valuation, and dates. Filter and export to CSV. Keep this US Building Permits Scraper evidence alongside the original source in a reviewed infrastructure research workflow.

1. Choose the corresponding source target in this second Actor’s own input form; no automatic field transfer is configured.
2. Keep both original source URLs and observation dates in your review sheet; reconcile identities manually.

A published milestone, application or project listing does not establish construction completion, available capacity or investability. Match official project evidence and dates.